Carpark – Burnside State High School

ATTAIN was engaged by Evans Built to complete a small carpark construction inside the Burnside State High School. Only a 13 bay carpark, but it was built on the side of a hill requiring over 300m3 of materials to be imported and tiered up the hill to create a stable subgrade base from which to […]
Narangba Early Learning Centre

As part of the ongoing growth and expansion of the population around the Narangba area, a green field site was chosen for a new early learning centre. ATTAIN was engaged to complete all the earthworks and civil works on the project as early package were let and prior to the subdivision area being opened up […]
Carpark Construction – The Lakes College

Work in Progress Project – about 45% Complete ATTAIN was engaged by Woollam to complete this large carpark extension to the Lakes College. Whilst predominately a civil project there were a couple of other elements to the project requiring works by other trades to ensurethe carpark could be built as per design. ATTAINs scope of […]
Road Widening – Moreton Bay Council Region

This project was a requirement for operational works on the new Queensland Ambulance Station at Morayfield. Hutchinson Builders engaged ATTAIN to complete the roadwidening works which provided safe turning lanes into and out of the new ambulance station. Due to the prximity of an intersection with a TMR controlled road and general volumes of traffic […]
Good Samaritan Catholic College – Bli Bli

As part of Stage 4 development of the Good Samaritan Catholic College, ATTAIN was selected to complete all civil works associated with this stage. The broad scope of works for Stage 4 included; bulk earthworks for new building, new carpark extension, new culdesac turning road, bio retention basins, civil stormwater. The project was completed over […]
TMR Roadwidening – Beachmere

ATTAIN was enagged as part of the upgrade works to the Birali Steiner School in Beachmere to complete a roadwidening project on Beachmere road for TMR. The purpose of the roadwidening was to create a turning lane into Newman Road. ATTAINs scope of work was a fulle scope requirement to build the specified design which […]
Moffat Beach – Child Care Centre

ATTAIN completed all site clearing works, bulk excavations, civil stormwater, detailed excavations, retaining wall backfill, detention tank excavations and general site works support. This project had to work very closely with the builder on sequencing and design related issued to ensure the safe coordination of excavation works and retaining wall construction for a more than […]
Performing Arts Building – Burnside State High School

ATTAIN completed all site clearing works, bulk excavations, civil stormwater, access roads and carpark construction for the School’s new facility. This project was technically challenging, having to build a large Engineered piling platform that was tiered up a steep hill in order for piles to be installed ahead of deep basement style excavations. Once piling […]
Queensland Ambulance Service – Morayfield

ATTAIN completed all demolition, bulk earthworks, civil stormwater, carpark works and road widening as part of the project to deliver a new greenfields ambulance station to Morayfield. Bulk Earthworks were over an 8000 sqm area and included 2,500m3 of cut and 500m3 of fill. We had more than 2900 sqm of concrete carpark and driveways […]